Construction Sum
ca. 150 Mio. €
Client
Ernst & Young Financial Services, Warschau (Polen)
Duration
From 2007 to 2008Project Activities
Environmental consulting for the project coordinator E&Y during the feasibility study
Environmental and technical consulting for the EIA during the scoping phase
Supervision and final quality check for the EIA
Workshops and consultations with municipal authorities, planners and experts.
Contact
Dorsch International Consultants GmbH
München (Headquarters)
80687 München
Germany
Phone: +49 89 5797-0
Fax: +49 89 5797-800
E-Mail: info@dorsch.de
Description
Gdansk is one of the host-cities of the EURO 2012 (European Soccer Championship). Therefore a new stadium – following the UEFA regulations and requirements – is needed.
The award-winning architectural concept for the new stadium “Baltic Arena” including the preliminary design was already done. In addition, a feasibility study for a new land use and functional concept (including a trade fair and exhibition area and a local traffic study) was carried out.
The Environmental Impact Assessment Study (EIA) was part of the documents prepared for the feasibility study and to facilitate the project approval procedure.
The project area comprises the stadium and its surroundings with approx. 12 ha as well as more than 25 ha for transport and parking facilities, trade and commercial zones, hotel and catering trade areas.
DC Water and Environment was partner of a joint venture under the lead of Ernst & Young Financial Services, Warsaw. Our main duties covered general environmental consultancy, accompanying the feasibility study and quality assurance for the EIA.